
Year of Science
天天吃瓜 College of Arts and Sciences is celebrating a Year of Science!
天天吃瓜鈥檚 Ohio Employee Ownership Center (OEOC) will host the 30th Annual Ohio Employee Ownership Conference on Friday, April 29, at the Hilton West in Fairlawn, Ohio. The theme for the conference is 鈥淐elebrating Three Decades of Success: Growing the Employee鈥
天天吃瓜鈥檚 Ohio Employee Ownership Center Hosts 30th Annual Ohio Employee Ownership Conference
天天吃瓜鈥檚 Ohio Employee Ownership Center (OEOC) will host the 30th Annual Ohio Employee Ownership Conference on Friday, April 29, at the Hilton West in Fairlawn, Ohio. The theme for the conference is 鈥淐elebrating Three Decades of Success: Growing the Employee鈥Work in Progress:
Start forming elevator #2 (south).
Grade beam and pile caps along column line #17 between A and G is in progress.
Pile caps for elevator #2 are complete.
Installing pile caps for Stair #3.
Looking forward:
Steel erection sequence #1 will begin on鈥
4/14- ISB Construction Updates
Work in Progress: Start forming elevator #2 (south). Grade beam and pile caps along column line #17 between A and G is in progress. Pile caps for elevator #2 are complete. Installing pile caps for Stair #3. Looking forward: Steel erection sequence #1 will begin on鈥天天吃瓜 will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 天天吃瓜 Hotel and Conference Center.
KENT STATE TO HOST ICAM/I2CAM CONFERENCE MAY 16-18
天天吃瓜 will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 天天吃瓜 Hotel and Conference Center.Work in Progress:
Pulling wire throughout for branch circuits.
Installing duct on 1st floor.
Complete domestic water rough-in on the 2nd floor.
Sanitary piping rough-in has been completed on the 3rd floor.
Completing remaining framing throughout.
Starting door frame鈥
4/7- Smith Hall Renovation Updates
Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame鈥Work in Progress:
Forming lift 3 on elevator #1.
Working on retaining wall progressing south to column line A7.
Pile caps and foundations for elevator #2 are complete.
Looking forward:
Pour lift #3 on elevator #1 on 4/8/2016.
Steel delivery and erection begins for鈥
4/7- ISB/Williams Hall Construction Updates
Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for鈥天天吃瓜鈥檚 fourth annual Neuroscience Symposium will cover the latest research findings on 鈥淭he Neuroscience of The Social Brain鈥 on April 7-8 at the 天天吃瓜 Hotel and Conference Center located in downtown 天天吃瓜, Ohio.
天天吃瓜 State Holds Symposium on 鈥淭he Neuroscience of the Social Brain鈥 on April 7-8
天天吃瓜鈥檚 fourth annual Neuroscience Symposium will cover the latest research findings on 鈥淭he Neuroscience of The Social Brain鈥 on April 7-8 at the 天天吃瓜 Hotel and Conference Center located in downtown 天天吃瓜, Ohio.Image
Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she鈥檇 already earned a dual bachelor鈥檚 degree in physics鈥
Becoming a Rocket Scientist
Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she鈥檇 already earned a dual bachelor鈥檚 degree in physics鈥Work in Progress:
Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week.
Started working on forming elevator #2 (South).
Pouring elevator #1 second lift (North) today.
Continuing the installation of the basement鈥
3/24- Williams Hall/ISB Construction Updates
Work in Progress: Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement鈥Work in Progress:
First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun.
Room 101 & 104 electrical rough-in is at 90% complete.
Machine Shop electric panel installed and completed on Saturday 3/19.
Room 223 electrical鈥
3/24- Smith Hall Renovation Updates
Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical鈥Work in Progress:
Steam piping in the 3rd floor east mechanical room is 20% complete.
Steam condensate lines for the steam station and AHU#1 are in progress.
Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has鈥